      I am building a 5" gauge locomotive which will be fitted with a couple of injectors feeding water into the boiler via a top feed arrangement but in addition I am also considering fitting a tender hand pump for use as an emergency back-up. Problem is finding the best way to connect the water supply from the hand pump into the boiler given that the only possible location for an independent clack valve on the current boiler is make use of one of two wash-out bushes mounted low down on the backhead which would not ideal in terms of accessibility.

      As an alternative I have been considering the idea of inserting a Tee piece into one of the injector feed pipes leading to the top feed fitting but would like some assurance that this would be a practical solution. Does any have firsthand experience of such an arrangement?

      Advert
      #2020
      Greensands
      Participant
        @greensands

        Best way to connect the water supply into the boiler

        #536791
        Nigel Graham 2
        Participant
          @nigelgraham2

          I don't think there is any reason for the hand-pump not to share the top feed with an injector, but it may result in not being able to use all three feed methods at once.

          I would ask though if a pump adding its output pulses to the injector delivery, possibly at higher pressure than the injector can give, would prevent that injector from working properly.

          In emergencies you need all options!

          It would need extra clack valve on the top–feeds. A Tee-piece alone would not be enough if upstream from the top-feed clack-valve. You'd need a second clack-valve in the injector delivery, otherwise at least some of the water from the punp would escape through the injector overflow.

          For aesthetic reasons, it may be possible to arrange all this low down, adjacent to the injector, but it might call for a pipe size up from that used by the injector alone, and slightly larger top-feed clack-valve, to enable both devices to be used at once.

          From the boiler's point of view, feeding cold water into the firebox water-space is not good, though mechanically feasible. You need run a pipe back under the foot-plate to a suitable connection on the drag-beam. If you need install a feed in a back-head wash-out bush, it would be better to route an injector to it and send the pump water to the vacated top-feed. (An injector heats the water.)

        Viewing 3 posts - 1 through 3 (of 3 total)
        • Please log in to reply to this topic. Registering is free and easy using the links on the menu at the top of this page.

        Advert

        Latest Replies

        Home Forums Locomotives Topics

        Viewing 25 topics - 1 through 25 (of 25 total)
        Viewing 25 topics - 1 through 25 (of 25 total)

        View full reply list.

        Advert

        Newsletter Sign-up